Go-Live Readiness Gates

The transition of Angau Memorial Hospital to the live environment is managed by ten sequential readiness gates (G1–G10).

To protect patient safety and ensure technical stability, gates must be passed in chronological order. A later gate cannot be signed off while an earlier gate remains open.


1. Sequential Gates Checklist

GateFocus AreaSuccess Criteria SummarySign-off Required
G1InfrastructureServer deployed; database backups verified; local networks operational; power UPS active.Required
G2Identity & MPIMaster Patient Index active; duplicate warning thresholds configured; reception clerks signed off.Required
G3Clinical WorkflowConsultation SOAP notes active; ICD-10 database verified; doctor and nurse training complete.Required
G4Diagnostics & PharmacyLaboratory LIS, Radiology PACS, and Pharmacy modules active; four-eyes dispensing rules verified.Required
G5Inpatient & WardsWard beds registered; Medication Administration Record (MAR) active; ICU/NICU modules configured.Required
G6Security & RBACLeast-privilege permissions verified; department boundaries tested; Billing configurations locked.Required
G7Downtime & ResilienceWorkstations tested offline; sync conflict queues validated; paper fallback forms placed.Required
G8Training Verification100% of active pilot staff assessed and certified as competent; logs filed.Required
G9User Acceptance (UAT)Clinical leadership runs end-to-end simulated scenarios (S01–S25) without errors.Required
G10Handover ApprovedFormal handover signature document signed by hospital leadership and the MOANA lead.Required

2. Gate Verification Principle

IMPORTANT:

Chronological Dependency Rule No phase of the implementation will progress to live patient data until the corresponding gate is signed off by both the MOANA Implementation Lead and the Hospital IT/Clinical Representative.

graph LR
A[Phase 1: Foundation (G1-G2)] --> B[Phase 2: Clinical & Diagnostics (G3-G5)]
B --> C[Phase 3: Security & Downtime (G6-G7)]
C --> D[Phase 4: Training & Go-Live (G8-G10)]

3. Workflow for Recording Gate Approvals

Step 1Compile Gate Evidence Pack

Gather the technical checklist, training sign-off sheets, or test reports for the active gate.

Step 2Access System Administration Panel

Log in with your IT Administrator account. Open System Parameters and navigate to Implementation Readiness Gates.

Readiness Gates configuration dashboard
Readiness Gates configuration dashboard🔍 Click to enlarge

Step 3Apply Joint Digital Signature

Select the active gate. The MOANA Implementation Lead and the Hospital Representative must enter their passwords in the dual-signature fields, then click Approve and Progress.

Expected Result:

The gate transitions to "Approved" (Green). The system unlocks the configuration parameters and permissions required for the next gate in the sequence.